FIELD NOTES // ESTIMATING

How Much Does a Wood Fence Cost Per Foot in Missouri?

A documented Brookfield, Missouri project was billed at $2,365 for 58 linear feet of six-foot treated-wood privacy fence with one walk gate. That is $40.78 per recorded foot for the whole scope, including the gate. It is one August 2026 example, not a statewide rate.

By Get Your Fence On · SEPTEMBER 6, 2026 · 10 MIN READ

A wood privacy fence along the back of a lawn in front of tall trees

A wood privacy fence of the type in this cost example. Illustration only - the Brookfield figures in this article come from one matched invoice and job record, not from this photo.

1. What did the 58-foot Brookfield fence include?

The matched invoice and job record describe 58 linear feet of six-foot pressure-treated dog-ear privacy fence, a natural finish and one walk gate. The invoice specifies concrete-set 4x4 posts and three treated 2x4 rails. Its billed total includes $950 for materials and $1,415 for installation labor.

The invoice is dated August 23, 2026, and the internal job record identifies the same project and scope in Brookfield. These are customer-facing billed amounts, not our purchasing costs. This article does not present the invoice as a final-paid amount or a signed completion acceptance.

Read the scope before the number. The job record describes six-foot treated-pine privacy fence with dog-ear pickets, the posts set in concrete, and one walk gate, on a run recorded at 58 linear feet. That is a complete small fence: posts, rails, pickets, fasteners, concrete, a gate with its hardware, and the crew's time to set it plumb and straight. What it does not include is as important as what it does - no removal of an old fence, no rock, no long carry, no second gate.

The pickets on a treated-pine fence are rated for above-ground use; the posts, which sit in soil, carry the ground-contact use category the wood -preservation industry calls UC4A. That distinction is invisible in a finished fence and decisive ten years later, which is why a scope that names the post treatment is worth more than one that only names the wood.

Sources: AWPA - Use Category information for residential treated wood · SFPA - Pressure-treated Southern Pine: standards, specifications, applications · QUIKRETE - Setting posts (project guide) · Real Cedar (WRCLA) - Western Red Cedar fence specifications

A stack of sawn timber boards

Boards, rails, posts, fasteners and concrete are the material half of a wood fence; the labor to set it plumb and straight is the other. Illustration only.

2. How is the $40.78 per-foot figure calculated?

Divide the $2,365 billed project total by the 58 linear feet recorded in its scope: $2,365 divided by 58 equals $40.78 when rounded to cents. The numerator includes the gate and installation. This is a blended project ratio, not a separate price for fence panels or labor.

The record does not give a separate gate price or gate width. We therefore cannot subtract a gate allowance to produce a fence-only rate. We use the recorded 58-foot quantity without assuming whether the gate opening was counted within it.

The figure is the billed total divided by the recorded footage, nothing else. It includes the gate, because the gate was in the total, and it includes the labor, because the invoice was for a finished fence. That makes it a blended project rate, not a material price and not a fence-only price. It is shown that way on purpose: a per-foot figure is only honest when you can see what was divided by what.

If you wanted a fence-only rate you would subtract the gate from the total and the gate opening from the footage, and the number would move. The extension cost sheets do that separation for farm fence - materials on one line, labor on another, gates excluded - and reading one shows how much a single convention changes the result.

Sources: NIST - U.S. survey foot: revised unit conversion factors · Omni Calculator - Rectangle fence perimeter calculator · Iowa State Ag Decision Maker B1-75 - Estimated costs for livestock fencing · K-State AgManager - 2023 fence material and construction cost in Kansas

3. Is $40.78 a typical wood fence price across Missouri?

This single project cannot establish a typical Missouri price. It describes one treated- wood privacy build in Brookfield in August 2026. It does not measure other contractors, regions, seasons, wood species or heights. Use the example to understand a written scope , then obtain a current quote for your property.

A statewide average would need a defined sample and comparable jobs. Calling one invoice an average would hide the very differences that matter to a homeowner. We are publishing the amount, quantity, material, height, gate count and date together so the example can be checked in context.

No single job can be typical. Prices move with the wood specification, the height, the picket style, the number of corners and gates, the ground, the access and the season, and a fence in Brookfield in August tells you about that fence in Brookfield in August. Kansas State's fence-cost survey and Iowa State's cost sheet are the honest benchmarks for how prices spread, and both are careful to publish ranges and assumptions rather than a single figure.

Use the example for what it is: a documented, itemized real job that shows the arithmetic. Then get a quote written for your line. Missouri 's fence law and MU Extension's guide to it are the other reading worth doing first, especially where the fence sits on a boundary you share.

Sources: K-State AgManager - 2023 fence material and construction cost in Kansas · K-State - Fence building cost survey in Kansas (2019) · Iowa State Ag Decision Maker B1-75 - Estimated costs for livestock fencing · MU Extension G810 - Missouri Fence and Boundary Law Reference Guide

4. Can I multiply this rate by 100 feet for my yard?

Multiplying this project ratio by 100 would not establish the price of a 100-foot fence. The example includes one gate within one particular scope. Your layout may have different gates, corners, access and site work. Price the complete new layout instead of extending this historical ratio into a quote.

For a useful comparison, ask each contractor to measure the same proposed line and describe the same gate openings. A long straight run and several short runs around a patio are different layouts even when their totals match. Keep the layout beside the number.

You can, and the number you get will be wrong in a direction you cannot predict. A hundred feet with two gates and six corners costs more per foot than 58 feet with one gate and four corners; a hundred feet in a straight line on open ground with no gate costs less. The fixed parts of a fence - gates, corners, the first hour of setup - do not scale with footage, and the per-foot rate hides them.

What multiplies well is the method. Measure your runs, count your corners and gates , note the ground and the access, and ask for an itemized quote. The extension surveys and the post-setting guides both show why the same fence costs different amounts on different ground: depth, footing and terrain are inputs, not constants.

Sources: K-State AgManager - 2023 fence material and construction cost in Kansas · Iowa State Ag Decision Maker B1-75 - Estimated costs for livestock fencing · Omni Calculator - Rectangle fence perimeter calculator · QUIKRETE - Setting posts (project guide)

5. How do the wood, height and style affect the comparison?

Compare the same wood specification, finished height and board arrangement before comparing totals. This example is six-foot pressure-treated dog-ear privacy fence with a natural finish. A cedar fence, an overlapping board-on-board layout or a shorter picket fence changes the material specification, so this invoice does not price those alternatives.

Ask for the post type, rail detail and finish in writing . The photograph above shows a separate horizontal cedar project to illustrate how different a wood -fence layout can be. It is not a photograph of the treated-wood job used for the price calculation.

Treated southern pine is the value wood and the one the Brookfield example used. Cedar costs more, stays flatter and resists decay without treatment, and is the wood the cedar association's specifications describe for board-on-board and shadowbox work. Height changes everything above ground - a six-foot fence uses roughly a third more picket than a four-foot one and its posts carry more wind - and the style changes the picket count: board-on-board overlaps its pickets and uses noticeably more wood than a flat dog-ear fence, shadowbox alternates them on both faces.

Compare the same wood , the same height and the same style, and only then the totals. A quote for six-foot cedar board-on-board and a quote for six-foot pine dog-ear are quotes for two different fences, and the cheaper one is not the better deal unless it is the fence you wanted.

Sources: Southern Forest Products Association - Southern Pine Use Guide · AWPA Standard U1 - Use Category System (excerpt) · Real Cedar (WRCLA) - Best fence ideas: board-on-board, shadowbox and picket · Dunn Lumber - Best practices for building a Western Red Cedar fence · Long Fence - What is a shadowbox fence?

A line of fence posts running along a dirt track

Height and picket style change the wood in every foot of fence, so two quotes only compare when both name the same specification. Illustration only.

6. Which site costs are not defined by this example?

The matched records do not separately price removal, hauling, difficult access, rock excavation or a gate upgrade. Treat those items as unspecified in this example. Their absence from a short invoice description does not prove they were included, free or unnecessary on another property with a different fence line.

Before accepting a proposal, resolve the existing fence, any known buried obstructions, equipment access and cleanup scope. Ask which items have a fixed price and which require a written change if conditions differ. This is where two apparently similar per-foot numbers can stop describing the same work.

Removal and hauling of an old fence, rock or hardpan at post depth , a long carry from the street, a slope that forces stepping, and hand-digging near a marked utility line are all real costs that the Brookfield job did not have. Any one of them can move a small fence more than the choice of picket style. They are found on the site visit, not on a satellite image, and they belong on the quote as their own lines.

The frost line is a quiet one. Around Kansas City the adopted residential code puts it at thirty-six inches, and the Missouri frost-depth map shows it varying across the state; a post that stops short of it heaves a little every winter. Depth is a footing decision, and the quote should say what depth it assumes. The free 811 locate comes before any of this, and the lines it marks are public ones - private lines to a shed or a sprinkler are yours to point out.

Sources: Missouri 811 - Homeowners · Missouri 811 - Public vs. private utility lines · Kansas City Residential Code 2018, Chapter 4 Foundations (frost line) · Missouri Public Service Commission - State of Missouri frost depth map

7. What evidence is behind this Missouri cost example?

The example uses one actual company invoice matched to an internal job record for the same Brookfield project. Both records identify the footage, height, treated- wood privacy style and gate count. The invoice supplies the billed total. Customer identity, street address, payment details and internal costs are withheld from this article.

Method: records were checked on September 6, 2026. We kept one observation for this project and calculated total billed dollars divided by recorded linear feet. We did not pool an unspecified-unit estimate , a labor-only invoice or example estimating sheets into the comparison. Sample size: one project.

The internal job record reports zero approved change orders as of its August 24 update. This article does not claim a current payment status, independent inspection, final acceptance or market survey. More verified, comparable projects would be needed before publishing a broader price range.

The example rests on one company invoice matched to the internal job record for the same Brookfield property, with the footage, the scope and the billed total taken from those two documents rather than from memory. The arithmetic is printed so you can check it. Nothing has been rounded to make the rate look tidier, and the address is not published.

That is the standard this site tries to hold for numbers: a figure comes with what produced it, or it does not appear. The extension cost surveys hold the same standard for their tables, which is why they are cited here instead of a price guide that does not say where its numbers came from. The U.S. foot itself is defined by NIST, which is the only part of the calculation nobody has to verify.

Sources: K-State AgManager - 2023 fence material and construction cost in Kansas · Iowa State Ag Decision Maker B1-75 - Estimated costs for livestock fencing · K-State - Fence building cost survey in Kansas (2019) · NIST - U.S. survey foot: revised unit conversion factors

8. What an invoice does not tell you

The Brookfield number in this article is real and it is one job. What that invoice cannot show you is the day behind it: the ground, the access, how many corners, whether an old fence had to come out first, and whether the truck could park in the yard or at the curb. Two crews can bill the same total for two completely different days of work, and the per-foot figure that falls out at the end hides all of it.

Wood also does something vinyl and composite do not: it moves. Treated pine leaves the yard heavy and wet, and over the first summer it shrinks, twists a little and lightens by several shades. A fence that goes up with the boards butted tight will show daylight between them by August. That is not a defect and it is not somebody cutting corners; it is lumber behaving like lumber. What separates a good wood fence from a bad one is that somebody planned for the movement instead of being surprised by it.

Which is why we care so much about the part that never shows. Posts rated for ground contact, set below the frost line , in a hole wide enough for the concrete to bear against undisturbed soil , crowned so water runs off instead of standing on top. Do that and the fence is straight in ten years while the boards weather to gray. Skip it and the prettiest pickets in Missouri lean in the third winter.

So use the example for the arithmetic, not for the price . If you want a number for your yard, the fastest honest path is to send the runs, the corners, the gates and a couple of photos of the ground, and let somebody walk it. Everything else is guessing with extra steps, and guessing is what produces the quotes that change after the digging starts.

Sources: USDA Forest Products Laboratory - Wood Handbook · American Wood Protection Association - use categories for ground contact · Preserved Wood Council - treated lumber in exterior use · University of Missouri Extension - fencing and exterior wood · Missouri Attorney General - home repair and contractor complaints

9. Ten years of a wood fence, and what it asks of you

A treated-pine privacy fence installed properly in Missouri will stand for decades , and it will not look the same the whole time. Left alone it weathers to a soft gray in about two years and stays there. Sealed or stained every few years it holds more color and sheds more water. Both are legitimate choices; only one of them is a recurring Saturday, and it is worth deciding which one you are before you buy the fence.

The maintenance that actually matters is not cosmetic. Keep dirt and mulch off the bottom of the pickets, keep sprinklers from spraying the same panel every night, and walk the line once a year looking for a nail that has backed out or a rail that has cupped. Ten minutes a year prevents most of the failures we get called about, and none of it requires a ladder.

Hardware is the quiet cost. Gates are the moving part of a wood fence and the part that gets used every day, so hinges, latches and the fasteners holding them are where cheap shows up first. Stainless or properly coated hardware on a cedar gate is a few dollars against a gate that sags in year three and gets adjusted forever after.

Then there is the repair story, which is wood 's real advantage. A cracked vinyl panel is a replacement panel; a split picket is a two-dollar board and ten minutes. Over a decade that difference is worth money, and it is the reason plenty of people who can afford anything still put up a wood fence and expect to touch it occasionally.

Sources: USDA Forest Products Laboratory - Wood Handbook · American Wood Protection Association - use categories for ground contact · Preserved Wood Council - treated lumber in exterior use · National Weather Service Kansas City - local climate data · University of Missouri Extension - fencing and exterior wood

10. How do I get a wood fence price for my Missouri property?

Start with the property location, approximate fence runs, preferred height and style, and the number and width of gates. Add photos of the line and explain removal or access needs. Then arrange an on-site measure and request a written scope with a current total for that specific layout.

Our planning calculator helps organize the fence details; an incomplete range or materials allowance is not an installed quote. Use the free on-site estimate request to have the actual line assessed. Bring the same scope to any comparison so you can see what each total buys.

Send the address, a sketch with each run measured and the corners marked, the wood , height and style you want, and each gate by width and what has to pass through it. Add photos of the line, the slope, anything to be removed and the way a truck gets in. Note anything buried that you know of. Then request the free locate through Missouri 811 and, if you can, find your survey pins.

The Jackson County parcel viewer, or your county's equivalent, gives you the lot dimensions to check your sketch against, and MU Extension's fence-law guide tells you what a shared boundary does and does not allow. The visit does the rest, and the quote that follows is written for your fence rather than for the one in Brookfield.

Sources: Missouri 811 - Homeowners · Jackson County, Missouri Parcel Viewer · Missouri Standards for Property Boundary Surveys (2021) · MU Extension G810 - Missouri Fence and Boundary Law Reference Guide

Plan your fence

Compare wood fence styles

Where we install fences in Missouri and Kansas

What changes a fence quote

Build your fence estimate

Request a free on-site estimate

Every job is different. The only number worth acting on is the one written after somebody walks your line.

BUILD AN ESTIMATE Call (573) 355-2711

KEEP READING

INSTALLATION

How Deep Should Fence Posts Be?

Our usual starting point is 30-36 inches, but the fence, the ground and the required footing detail decide the actual depth.

Read it

All posts

PREFER TO TALK IT THROUGH?

We are glad to start your estimate over the phone.

Call or text (573) 355-2711